Governor Jindal said, “We got word yesterday that federal officials were going to shut down our dredging operations on the North Chandeleur Islands and those operations were indeed stopped under the federal government’s command at 6PM last night.
“Our request here today is simple. We are again calling on the federal government to allow us to continue these dredging operations as we mobilize pipe for another two miles – which will take around just seven more days. Getting this pipe in place without stopping the dredging operations will allow us a seamless transition as we move the dredge to a new borrow site. After this pipe is in place, our dredger can disconnect and move to the next site where it can then resume dredging operations in just one day.
“We have told Col. Lee of the Army Corps of Engineers and every federal agency that we are in an emergency situation here. This is a disaster for our state. Days count. Hours count. We cannot wait for more conference calls and meetings for discussions. We need to adapt to the situation on the ground and continue our dredging operations for as long as possible until we can move to the next borrow site and continue to create sand boom.
To date, more than 690,000 cubic yards of material have been transported for the eastern and western reaches of the sand berm project on the North Chandeleur Islands. This includes approximately 90,000 cubic yards on the western side. A total of 5,000 feet of sand berm has been created at the site. The state has also dredged over 2.5 miles on East Grand Terre.
The Governor added, “We have jumped through every hoop that the federal government has placed in front of us since this spill started. On May 2, we submitted our initial boom plan to the Incident Command Post since there was not a plan. When BP and the Coast Guard were unable to provide the appropriate boom resources, we began developing innovative solutions like Tiger Dams, air-dropping sand bags, Hesco baskets, opening all freshwater diversions, vacuum barges and many other alternatives.
“On May 11th, we submitted a proposal to the regulatory agencies, BP and the Coast Guard to approve our sand berms. It took almost a month for the federal government to approve the plan and make BP pay for the work. Meanwhile, we had millions of gallons of oil covering our wetlands, killing our wildlife and forcing our people out of work.”
At a press conference following the tour of the dredging site, the Governor highlighted a picture of the Chandeleur Islands from 2001 to 2005 that shows the erosion of the area. Governor Jindal noted that The U.S. Fish and Wildlife Service own these islands and they are supposed to be a wildlife refuge.
Governor Jindal said, “People used to live on these islands. It was a fishing community and even had some farming. From the mid-90s until recently, the islands lost up to 300 feet per year under U.S. Fish and Wildlife Service management. Now, this same agency has concerns that we are not being sensitive to the islands by wanting to continue to dredge for seven more days to ensure a smooth transition? They have not invested a penny in this area and are allowing it to erode at extraordinary rates. Meanwhile, they invest millions in other refuges in other parts of the country.
“Louisiana's coast is one our most important resources. That is why we are fighting so hard to protect our wetlands, protect our fisheries and birds and to protect our way of life from this oil spill – with these sand booms.
“We have said from the beginning that we would backfill any dredging that would adversely affect these islands. That commitment still stands. Shutting down dredging operations while oil continues to hit our shores and the oil continues to flow into the Gulf is absolutely absurd. We need to act now.
“The area where the state was dredging remains within the area permitted by the federal government. When the dredging contractor began operations, the U.S. Fish and Wildlife Service voiced objections to the location of the dredge. In an effort to prevent delay to the project, we worked out an agreement that would provide for backfilling the dredge site and the movement of the dredge vessel to a new location. The state remains committed to moving the dredge to another location within the permitted area and backfilling the first dredge site.”
TEXT and PHOTO CREDIT: Office of the Governor || PO Box 94004, Baton Rouge, LA 70804 || Contact the Governor||
No comments:
Post a Comment